Capital Campaign

150,000!ELLA REDKEY CAPITAL CAMPAIGN FUNDRAISING GOALS REACHED!

Capital Campaign Includes:

  • - Creation of a Recreational Plaza around the pavilion with a safe ADA walkway with enhanced amenities (estimated cost: $80,000)

  • - Renovation of the locker rooms (estimated cost: $70,000)

  • - Replacement of the outdoor water slide (estimated cost: $140,000)


Projects Timeline

Lower Recreation Plaza

  • Phase 1
    • Pavilion, concrete expansion and ADA walkway to New Pavilion completed October 2022
  • Phase 2
    • ADA walkway to the Pool deck
    • Bring utilities to Pavilion (gas, water, electric)
    • Landscaping around pavilion and lower area
    • Repositioning Entry Gate
    • All to be completed 2023-2024
  • Phase 3
    • Removal and Upgrade of fencing
    • Concrete steps to pool decking
    • Addition of guard railing on steps and walkways
    • All to be completed 2026-2027

Bathhouse Renovations

Part 1 - February 23 through February 28

Part 2 - April 2023

Waterslide Replacement

Ordering Slide Parts

 - Spring 2023

Demolition and Installation of new waterslide

 - Fall/Winter 2023

2023-02-08 Ella Redkey Pool Reaches Capital Campaign Goal_Page_1

2023-02-08 Ella Redkey Pool Reaches Capital Campaign Goal_Page_2


  1. 1 IMG_2170
  2. 2 IMG_2178
  3. 3 IMG_2180
  4. 4 IMG_2198
  5. 5 IMG_2207
  6. 6 IMG_2215
  7. 7 IMG_2240
  8. 8 IMG_2261
  9. 9 IMG_2275
  10. 10 IMG_2297
  11. 11 IMG_2309
  12. 12 IMG_2332
  13. 13 IMG_2404
  14. 14 IMG_2406
  15. 15 IMG_2448
  16. 16 IMG_2461
  17. 17 Renders for Posters - Stairs in pencil
  18. 18 Exterior Renders - Overview at Night - Copy
  19. 19 Renders for Posters - Exterior Branding - Copy
  20. 20 Renders for Posters - Recreation Plaza Entrance with Fence
  21. 21 Renders for Posters - Recreation Plaza
  22. 22 Renders for Posters - Interior Locker Room
  23. 23 Renders for Posters - Interior Entrance